Monday, October 18, 2010

Investment Property Complete

My investment property is now complete, The house is finished and we have our first tennat aboard.

Here are a few pictures of the completed house


.



I am happy with the finished result. Now We must relax and maintain the property.



Friday, September 3, 2010

Final Inspection of our Pivotal investment home

Today marked the final inspection of our Pivotal investment home. I  was happy that all the defects had been adequately fixed. The house was looking good. But unfortunately the turf that was laid a few days ago is dying and looks very brown.



 I rang our new property manager, and she suggested to call their Lawn Maintenance Man, Terry and he agreed to water the lawns for an hour on Saturday for $40.

Thursday, August 26, 2010

Practical Completion of Pivotal home

Well Today was Practical completion date! At 1.30pm we had a meeting with Pivotal homes to inspect the property, Mostly the house was complete, but with the rain, they had been unable to lay the turf down, and they will still laying the turf today. We also found several small faults which Pivotal homes will fix over the next couple of days

Standing at the front door of the new house

From the corner view of windaroo outlook

Tuesday, August 24, 2010

Final days before practical completion


I have been interviewing property managers, but have chosen Jill Lieper from Remax to be my property manager.

Our invesment house   

  

Air Conditiong unit
Water tank installed
Alfresco

Fixing stage

The property is almost complete, the fixing stage is complete, and we have been given a practical completion date. I have been busy organizing the building insurance and property management.

Stone top benchs
Ceiling fans
Letter box completed

Thursday, July 29, 2010

The enclosed stage is now completed!

The enclosed stage is now completed!


Hi Michael!
We have now reached enclosed stage at your property, Lot 40 Vista Circuit at Bahrs Scrub.  Please see attached invoice.
Photographs will be taken and uploaded into your gallery later this week.
In the mean time, can you please send me a Westpac Progress Payment Authority form for enclosed stage? I will match it with the invoice and forward to Westpac for payment.
Payment is due within 5 working days (as per our contract), so your prompt attention to this matter would be greatly appreciated
Please let me know if you have any queries!
Kind Regards,
Sarah Allie
Construction Administrator & Progress Payments
 
Level 5,33 Elkhorn Avenue
Surfers Paradise Qld 4217
PO Box 8146 Gold Coast MC Qld 9726
P: 07 5504 5047  F: 07 5504 7322


The letterbox




  

 
Plastering the walls