Pivotal homes does the plumbing works

Work has now begun on our investment property, I was concerned that nothing was happening, but on Friday I received an email to say the plumbing work was done.


I just wanted to put in writing for you that the following has now been completed on your property:

  • Your retaining wall has been completed
  • Site has been fully set out
  • Piers have been completed
  • Under slab drainage has been completed
  • Slab preparation has been completed (steel, waffle pods etc)

The last thing we need to do is pour the slab which is a fast process, and Steffen anticipates that it will be done early next week. Photos will then be taken and uploaded into your photo gallery on the Pivotal Homes website, at which point I’ll e-mail you a username and password so you can view them.

Let me know if you have any queries.

Thankyou,



Kind Regards,

Courtney Irwin
Client Relations Manager & Progress Payments
 Level 5,33 Elkhorn Avenue
Surfers Paradise Qld 4217
PO Box 8146 Gold Coast MC Qld 9726
P: 07 5504 5047  F: 07 5504 7322



It looks our neighbours have now had their slab poured

1 comment:

  1. Thats great to see the work done so far! The weather has definitely not held things up for you...
    Looking forward to seeing more as it progresses.