Thursday, July 29, 2010

The enclosed stage is now completed!

The enclosed stage is now completed!


Hi Michael!
We have now reached enclosed stage at your property, Lot 40 Vista Circuit at Bahrs Scrub.  Please see attached invoice.
Photographs will be taken and uploaded into your gallery later this week.
In the mean time, can you please send me a Westpac Progress Payment Authority form for enclosed stage? I will match it with the invoice and forward to Westpac for payment.
Payment is due within 5 working days (as per our contract), so your prompt attention to this matter would be greatly appreciated
Please let me know if you have any queries!
Kind Regards,
Sarah Allie
Construction Administrator & Progress Payments
 
Level 5,33 Elkhorn Avenue
Surfers Paradise Qld 4217
PO Box 8146 Gold Coast MC Qld 9726
P: 07 5504 5047  F: 07 5504 7322


The letterbox




  

 
Plastering the walls

Friday, July 23, 2010

Bricks are Up and the Bench top is Down

I went out today to see some good progress on our property, The brick building is going well. I met with some of the Brickies who where building the house it was good to chat.




These are the bricks for our house




View to our neighbours            

The stone top benchs are in place


This is the stone bench top     

 This is an email from Pivotal homes
I’ve just checked the latest construction update and the only thing left to be done on your property before we claim “enclosed stage” is the rest of the brickwork. We should be claiming enclosed stage early next week.

From enclosed stage, completion is about 6 weeks away (weather permitting). It’s important that we have good weather during the period that we are doing your fencing, landscaping and putting the finishing touches on your property because as you can imagine, it’s very difficult to lay turf and put plants in the ground if it’s pouring rain! We’ve had a good run of luck though, and I’m optimistic that it’s 6-7 weeks from completion as of today.

We will complete fixing stage in approximately 3 weeks from now, and that’s when we’ll book in a “practical completion inspection date”. You’ll be given at least 2 weeks notice before this inspection, and you’ll be mailed a letter about this explaining everything that will happen.

Everything is moving along nicely at the moment though – Let me know if you’d like any further information.