I’ve just checked the latest construction update and the only thing left to be done on your property before we claim “enclosed stage” is the rest of the brickwork. We should be claiming enclosed stage early next week.
From enclosed stage, completion is about 6 weeks away (weather permitting). It’s important that we have good weather during the period that we are doing your fencing, landscaping and putting the finishing touches on your property because as you can imagine, it’s very difficult to lay turf and put plants in the ground if it’s pouring rain! We’ve had a good run of luck though, and I’m optimistic that it’s 6-7 weeks from completion as of today.
We will complete fixing stage in approximately 3 weeks from now, and that’s when we’ll book in a “practical completion inspection date”. You’ll be given at least 2 weeks notice before this inspection, and you’ll be mailed a letter about this explaining everything that will happen.
Everything is moving along nicely at the moment though – Let me know if you’d like any further information.